Notre-Dame Street - Expansion of Electrical System Capacity
Federal contribution
$2.8M
$2,785,557
Federal share30%
of $9.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 18, 2010
2011
Built
Approved 3 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Montreal Port Authority
- Construction start
- May 5, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start2 weeks lateforecast Apr 19, 2010
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39777 in the federal list. How to read these figures.