Notre-Dame Street - Expansion of Electrical System Capacity

Montréal, Quebec

completeMarineISF
Federal contribution
$2.8M
$2,785,557
Federal share30%

of $9.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 18, 2010
2011
Built

Approved 3 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Montreal Port Authority
Construction start
May 5, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Apr 19, 2010