Back to projects

Repairs along Chemin du Lac Taureau

Saint-Michel-des-Saints, Quebec

completeHighways and RoadsCC Top Up
Federal contribution
$1.2M
$1,206,697
Federal share32%

of $3.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 1, 2010
2011
Built

Approved 2 months before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Construction start
Oct 25, 2010(actual)
Construction end
Sep 30, 2011(actual)

Also in Saint-Michel-des-Saints

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39800 in the federal list. How to read these figures.