Repairs along Chemin du Lac Taureau
Saint-Michel-des-Saints, Quebec
Federal contribution
$1.2M
$1,206,697
Federal share32%
of $3.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 1, 2010
2011
Built
Approved 2 months before the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Municipality of Saint-Michel-Des-Saints
- Construction start
- Oct 25, 2010(actual)
- Construction end
- Sep 30, 2011(actual)