Rehabilitation of the municipal outdoor rink
Saint-Michel-des-Saints, Quebec
Federal contribution
$28,666
Federal share33%
of $86.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 10, 2018
20192020
Built
Approved 2 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Saint-Michel-des-Saints
- Construction start
- Aug 1, 2019(actual)
- Construction end
- Feb 4, 2020(actual)
Against the original forecast
- Construction start14 months lateforecast Jun 1, 2018
- Construction end16 months lateforecast Sep 30, 2018
Also in Saint-Michel-des-Saints