Back to projects

Highway 401 - Essex Road to Bloomfield Road Eastbound Lanes

Chatham-Kent, Ontario

completeHighways and RoadsISF
Federal contribution
$2.5M
$2,450,000
Federal share50%

of $4.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 7, 2010
Built

Approved 2 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Ontario
Construction start
Sep 2, 2010(actual)
Construction end
Oct 28, 2010(actual)

Also in Chatham-Kent

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39819 in the federal list. How to read these figures.