HVAC upgrade for schools and childcare; Water fill station; Window Replacement
Federal contribution
$3.0M
$2,974,902
Federal share80%
of $3.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
202220232024
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- St Clair Catholic District School Board
- Construction start
- Feb 18, 2021(actual)
- Construction end
- Dec 31, 2023(actual)
Also in Chatham-Kent
- Flood Mitigation along Thames and Sydenham Rivers: Slope Stabilization and Levee to Retain Recurrent River Flooding$16.6M
- YMCA of Chatham-Kent Facility Renewal$4.2M
- Highway 401 - Essex Road to Bloomfield Road Eastbound Lanes$2.5M
- HVAC Upgrades and/or Window Replacement$2.3M
- Wifi Infrastructure Retrofit; Window Replacement; Water Bottle Filling Station; Cooling Centre$2.2M