Back to projects

Science North - Building Exterior Retrofit

Greater Sudbury, Ontario

completeCultureISF
Federal contribution
$500,000
Federal share50%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 12, 2010
2011
Built

Approved 6 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Ontario
Construction start
Mar 12, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Apr 1, 2010
  • Construction end7 weeks lateforecast Sep 10, 2011

Also in Greater Sudbury

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39822 in the federal list. How to read these figures.