Back to projects

Highway 9 - Clifford to Mildmay

South Bruce, Ontario

completeHighways and RoadsISF
Federal contribution
$811,139
Federal share41%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 7, 2010
Built

Approved 2 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Ontario
Construction start
Sep 2, 2010(actual)
Construction end
Nov 27, 2010(actual)

Against the original forecast

  • Construction end6 weeks lateforecast Oct 15, 2010

Also in South Bruce

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39825 in the federal list. How to read these figures.