Bridge and Roadway Reconstruction on Adam Street
Federal contribution
$764,963
Federal share50%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 19, 2019
20202021202220232024
Built
Approved 4 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Municipality of South Bruce
- Construction start
- Jul 1, 2022(actual)
- Construction end
- May 23, 2024(actual)
Against the original forecast
- Construction start18 months lateforecast Jan 1, 2021
- Construction end5 weeks earlyforecast Jun 30, 2024
Also in South Bruce