Construction of an intergenerational/aquatic centre
Federal contribution
$5.7M
$5,682,804
Federal share33%
of $17.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 19, 2010
201020112012
Built
Approved 3 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- City of Côte-Saint-Luc
- Construction start
- Oct 4, 2010(actual)
- Construction end
- Oct 23, 2012(actual)
Against the original forecast
- Construction start6 months lateforecast Apr 1, 2010
- Construction end14 months lateforecast Aug 31, 2011
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39843 in the federal list. How to read these figures.