Waterworks improvements and pavement repairs on Chemin de la Côte Sud

Boisbriand, Quebec

completeDrinking WaterCC Top Up
Federal contribution
$1.5M
$1,469,936
Federal share30%

of $4.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2010
2011
Built

Approved 5 months before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Boisbriand
Construction start
Jul 6, 2010(actual)
Construction end
Jul 31, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jun 1, 2010