Modernization of the operating room ventilation system
Federal contribution
$800,000
Federal share80%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 28, 2024
20232024
Built
Approved 2.4 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux des Laurentides
- Construction start
- Nov 7, 2022(actual)
- Construction end
- Mar 29, 2024(actual)
Against the original forecast
- Construction start4 months lateforecast Jul 11, 2022
Also in Boisbriand