Construction of a community centre
Federal contribution
$541,745
Federal share28%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 19, 2010
2011
Built
Approved 7 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Cap-Santé
- Construction start
- Sep 7, 2010(actual)
- Construction end
- Aug 21, 2011(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 7, 2010
Also in Cap-Santé
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39850 in the federal list. How to read these figures.