Water Systems Upgrades

Cap-Santé, Quebec

completeDrinking WaterGIS
Federal contribution
$202,813
Federal share40%

of $507.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 4, 2020
2021
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Cap-Santé
Construction start
Nov 12, 2020(actual)
Construction end
Nov 15, 2021(actual)

Against the original forecast

  • Construction start5 months lateforecast Jun 1, 2020
  • Construction end16 months earlyforecast Mar 31, 2023