Restoration of Sisco Memorial Church

Coaticook, Quebec

completeCultureCC Top Up
Federal contribution
$51,627
Federal share32%

of $160.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 12, 2010
2011
Built

Approved 2 months before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Coaticook
Construction start
Sep 20, 2010(actual)
Construction end
Jul 31, 2011(actual)

Against the original forecast

  • Construction start6 months lateforecast Mar 11, 2010
  • Construction end2 months lateforecast May 31, 2011

Also in Coaticook

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39852 in the federal list. How to read these figures.