Implementation of flood risk management measures for the City of Coaticook

Coaticook, Quebec

completeDisaster MitigationGIS
Federal contribution
$1.8M
$1,778,501
Federal share40%

of $4.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 15, 2023
2023
Built

Approved 16 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Coaticook
Construction start
Aug 15, 2022(actual)
Construction end
Oct 5, 2023(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 4, 2022
  • Construction end3 weeks lateforecast Sep 15, 2023