Implementation of flood risk management measures for the City of Coaticook
Federal contribution
$1.8M
$1,778,501
Federal share40%
of $4.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 15, 2023
2023
Built
Approved 16 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Coaticook
- Construction start
- Aug 15, 2022(actual)
- Construction end
- Oct 5, 2023(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jul 4, 2022
- Construction end3 weeks lateforecast Sep 15, 2023