Memphrémagog Regional Sports Centre

Magog, Quebec

completeSportCC Top Up
Federal contribution
$4.1M
$4,054,133
Federal share33%

of $12.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 9, 2010
2011
Built

Approved 2 months before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Construction start
Nov 15, 2010(actual)
Construction end
Sep 1, 2011(actual)

Against the original forecast

  • Construction start7 months lateforecast May 1, 2010