Water Systems Upgrades
Federal contribution
$1.9M
$1,936,798
Federal share40%
of $4.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
202120222023
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of Magog
- Construction start
- Jun 1, 2020(actual)
- Construction end
- Nov 30, 2022(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Jul 7, 2020