Highway 6 - Tobermory Towards Mar

Bruce, Ontario

completeHighways and RoadsISF
Federal contribution
$6.8M
$6,834,753
Federal share34%

of $20.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 7, 2010
2011
Built

Approved 2 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Ontario
Construction start
May 3, 2010(actual)
Construction end
Jul 15, 2011(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jun 1, 2010