Back to projects

Bruce County Rail Trail Proposal

Bruce, Ontario

completeRecreationNRT
Federal contribution
$80,000
Federal share47%

of $170.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2016
2016
Built

Approved 13 months before the announcement.

Program
National Recreational Trails Program
Ultimate recipient
County of Bruce
Construction start
Jun 15, 2015(actual)
Construction end
Dec 10, 2015(actual)

Also in Bruce

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50874 in the federal list. How to read these figures.