Renovation of La Salicorne inn

Les Îles-de-la-Madeleine, Quebec

completeTourismCC Top Up
Federal contribution
$412,333
Federal share33%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 26, 2010
2011
Built

Approved 8 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Club Vacances "Les Iles"
Construction start
Oct 4, 2010(actual)
Construction end
Jul 31, 2011(actual)

Against the original forecast

  • Construction start7 months lateforecast Mar 1, 2010

Also in Les Îles-de-la-Madeleine

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39969 in the federal list. How to read these figures.