Schedule
Announced and approvedMay 8, 2017
201820192020
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Les Îles-de-la-Madeleine
- Construction start
- May 1, 2019(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction end4 months lateforecast Nov 30, 2019
Also in Les Îles-de-la-Madeleine
- Construction of a sports centre with two rinks$5.2M
- Shoreline protection work against coastal erosion in the Cap-aux-Meules sector of the Municipality of Les Îles-de-la-Madeleine$3.6M
- Renovation and Expansion of the Maritime Museum$1.6M
- Water Systems Upgrades$639.8K
- Renovation of La Salicorne inn$412.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49151 in the federal list. How to read these figures.