Program for the renewal of drinking water and wastewater pipes
Federal contribution
$169,378
Federal share31%
of $546.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 8, 2010
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of La Prairie
- Construction start
- Jun 9, 2009(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 6, 2009
Also in La Prairie
- Reconstruction of the Clairiere IV Pumping Station$1.4M
- La Prairie parking lot - Construction$905.2K
- Program for the renewal of drinking water and wastewater pipes$541.6K
- Program for the renewal of drinking water and wastewater pipes$488.1K
- Development of a synthetic surface soccer-football field$479.2K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39988 in the federal list. How to read these figures.