Reconstruction of the Clairiere IV Pumping Station
Federal contribution
$1.4M
$1,429,200
Federal share40%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
20212022
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- La Prairie
- Construction start
- Jul 16, 2020(actual)
- Construction end
- Feb 8, 2022(actual)
Against the original forecast
- Construction start4 months earlyforecast Nov 16, 2020
- Construction end3 months lateforecast Nov 2, 2021
Also in La Prairie
- La Prairie parking lot - Construction$905.2K
- Program for the renewal of drinking water and wastewater pipes$541.6K
- Program for the renewal of drinking water and wastewater pipes$488.1K
- Development of a synthetic surface soccer-football field$479.2K
- Program for the renewal of drinking water and wastewater pipes$169.4K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57021 in the federal list. How to read these figures.