Program for the renewal of drinking water and wastewater pipes

Québec, Quebec

completeWastewaterISF
Federal contribution
$1.6M
$1,608,783
Federal share31%

of $5.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 8, 2010
20102011
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Québec
Construction start
Jun 9, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 6, 2009
  • Construction end7 months lateforecast Mar 31, 2011