Program for the renewal of drinking water and wastewater pipes
Federal contribution
$321,920
Federal share31%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 8, 2010
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Terrebonne
- Construction start
- Jun 9, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 6, 2009
- Construction end7 months lateforecast Mar 31, 2011
Also in Terrebonne
- Upgrade of electrical input and addition of transformer$4.6M
- Program for the renewal of drinking water and wastewater pipes$2.5M
- Realignment of Saint-Sacrement Street and revitalization of Des Seigneurs Boulevard$789.8K
- Roof repairs in Terrebonne$568.3K
- Upgrade of mechanical and electrical systems$513.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40136 in the federal list. How to read these figures.