Upgrade of electrical input and addition of transformer

Terrebonne, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$4.6M
$4,560,000
Federal share80%

of $5.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Mar 21, 2022(actual)
Construction end
Jul 18, 2023(actual)

Against the original forecast

  • Construction start6 months lateforecast Oct 4, 2021
  • Construction end5 weeks earlyforecast Aug 23, 2023