Upgrade of electrical input and addition of transformer
Federal contribution
$4.6M
$4,560,000
Federal share80%
of $5.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux de Lanaudière
- Construction start
- Mar 21, 2022(actual)
- Construction end
- Jul 18, 2023(actual)
Against the original forecast
- Construction start6 months lateforecast Oct 4, 2021
- Construction end5 weeks earlyforecast Aug 23, 2023
Also in Terrebonne
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58977 in the federal list. How to read these figures.