Reconstruction of the Durocher Pumping Station

Terrebonne, Quebec

completeWastewaterGIS
Federal contribution
$460,840
Federal share40%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 17, 2020
20212022
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Terrebonne
Construction start
Oct 5, 2020(actual)
Construction end
Apr 1, 2022(actual)

Against the original forecast

  • Construction end4 months lateforecast Nov 25, 2021

Also in Terrebonne

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57011 in the federal list. How to read these figures.