Program for the renewal of drinking water and wastewater pipes

Sherbrooke, Quebec

completeWastewaterISF
Federal contribution
$2.1M
$2,139,646
Federal share31%

of $6.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 8, 2010
20102011
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Sherbrooke
Construction start
Jun 9, 2009(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 6, 2009