Back to projects

Hamlet of Aneroid Water Line Replacement

Ponteix, Saskatchewan

completeDrinking WaterCC Top Up
Federal contribution
$4,666
Federal share33%

of $14.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 9, 2010
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Nov 5, 2010(actual)
Construction end
Nov 12, 2010(actual)

Against the original forecast

  • Construction start5 months lateforecast Jun 1, 2010
  • Construction end2 months lateforecast Aug 31, 2010

Also in Ponteix