Notukeu Regional Park Board Authority - Park Washrooms/Changerooms
Federal contribution
$110,000
Federal share40%
of $275.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 6, 2021
20222023
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Notukeu Regional Park Board Authority
- Construction start
- Mar 21, 2022(actual)
- Construction end
- Jun 30, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast Dec 7, 2021
- Construction end9 months earlyforecast Mar 31, 2024
Also in Ponteix
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59323 in the federal list. How to read these figures.