Highway 3 - Paulson Bridge to Avalanche Gate
Christina Lake, British Columbia
Federal contribution
$1.1M
$1,091,958
Federal share50%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 1, 2010
Built
Approved 5 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Jun 21, 2010(actual)
- Construction end
- Jul 26, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 1, 2010
- Construction end5 weeks earlyforecast Aug 30, 2010