Christina Lake Water System Upgrades
Christina Lake, British Columbia
Federal contribution
$402,500
Federal share50%
of $805.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional District of Kootenay Boundary
- Construction start
- Oct 10, 2017(actual)
- Construction end
- Oct 31, 2018(actual)
Also in Christina Lake