Highway 99 - Regional Boundary to Long Cayoosh Bridge
Federal contribution
$969,696
Federal share50%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 1, 2010
Built
Approved 5 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Jun 1, 2010(actual)
- Construction end
- Sep 24, 2010(actual)
Also in Lillooet