Highway 99 - Fountain Slide Slope - Stabilization and dainage

Lillooet, British Columbia

completeHighways and RoadsISF
Federal contribution
$706,832
Federal share32%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 19, 2010
ApprovedSep 8, 2010
2011
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 11, 2010(actual)
Construction end
Apr 29, 2011(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Sep 1, 2010
  • Construction end4 weeks lateforecast Mar 31, 2011