Florence Lake Forest Service Road

Mission, British Columbia

completeHighways and RoadsISF
Federal contribution
$510,000
Federal share50%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2010
2011
Built

Approved 5 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 23, 2010(actual)
Construction end
Jul 31, 2011(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 30, 2010
  • Construction end4 weeks earlyforecast Aug 31, 2011

Also in Mission

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40253 in the federal list. How to read these figures.