Back to projects

Brampton Social Services Centre

Brampton, Ontario

completeOtherISF
Federal contribution
$1.6M
$1,579,620
Federal share36%

of $4.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 8, 2010
ApprovedJul 21, 2010
20112012
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Mar 23, 2011(actual)
Construction end
Dec 31, 2011(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Nov 30, 2011

Also in Brampton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40413 in the federal list. How to read these figures.