Development of the Beauport Area
Federal contribution
$1.9M
$1,887,877
Federal share50%
of $3.8M total eligible cost; the rest comes from other partners.
Approved 8 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Québec Port Authority
- Construction start
- Sep 5, 2010(actual)
- Construction end
- Nov 30, 2010(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 15, 2010
- Construction end2 weeks lateforecast Nov 15, 2010
Also in Québec
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40544 in the federal list. How to read these figures.