Watermain Renewal - Phase 3
Federal contribution
$527,062
Federal share33%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 8, 2011
2011
Built
Approved 10 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Saskatoon
- Construction start
- Oct 18, 2010(actual)
- Construction end
- Aug 30, 2011(actual)
Against the original forecast
- Construction start3 months lateforecast Jul 15, 2010
- Construction end4 weeks earlyforecast Sep 30, 2011
Also in Saskatoon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40555 in the federal list. How to read these figures.