Back to projects

Program for the renewal of drinking water and wastewater pipes

Baie-Saint-Paul, Quebec

completeWastewaterISF
Federal contribution
$455,726
Federal share31%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 22, 2010
20102011
Built

Approved 3 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Baie-Saint-Paul
Construction start
Jun 9, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 6, 2009
  • Construction end7 months lateforecast Mar 31, 2011

Also in Baie-Saint-Paul

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40590 in the federal list. How to read these figures.