Expansion and Upgrading of the Luc and Marie-Claude Arena
Federal contribution
$1.9M
$1,897,384
Federal share33%
of $5.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 6, 2021
202120222023
Built
Approved 3 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Baie-Saint-Paul
- Construction start
- Apr 7, 2022(actual)
- Construction end
- Mar 31, 2023(actual)
Also in Baie-Saint-Paul
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58121 in the federal list. How to read these figures.