Program for the renewal of drinking water and wastewater pipes

Weedon, Quebec

completeWastewaterISF
Federal contribution
$407,409
Federal share31%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 20, 2010
20102011
Built

Approved 3 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Municipality of Weedon
Construction start
Jun 9, 2009(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 6, 2009

Also in Weedon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40594 in the federal list. How to read these figures.