Renewal of water pipes
Federal contribution
$744,717
Federal share50%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 26, 2017
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Weedon
- Construction start
- Aug 24, 2017(actual)
- Construction end
- Oct 19, 2018(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 5, 2017