Renewal of water pipes

Weedon, Quebec

completeDrinking WaterCWWF
Federal contribution
$744,717
Federal share50%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 26, 2017
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Weedon
Construction start
Aug 24, 2017(actual)
Construction end
Oct 19, 2018(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 5, 2017