Arterial Road Rehabilitation in Various Locations in Edmonton
Federal contribution
$2.4M
$2,420,888
Federal share28%
of $8.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 19, 2009
ApprovedSep 1, 2010
20102011
Built
Approved 15 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Edmonton
- Construction start
- Sep 1, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Aug 1, 2010
- Construction end4 months lateforecast Dec 3, 2010
Also in Edmonton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40793 in the federal list. How to read these figures.