Southwest Quadrant Storm Water Collection Facility
Federal contribution
$237,585
Federal share21%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 20, 2010
2011
Built
Approved 3 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Regina
- Construction start
- Jul 4, 2011(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Jul 31, 2011
Also in Regina
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40907 in the federal list. How to read these figures.