Town of Lincoln Community Complex (Beamsville Arena and Library)
Federal contribution
$4.8M
$4,809,490
Federal share33%
of $14.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 29, 2011
201220132014
Built
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Town of Lincoln
- Construction start
- Dec 10, 2012(actual)
- Construction end
- Jun 10, 2014(actual)
Against the original forecast
- Construction start5 months earlyforecast Apr 30, 2013
- Construction end3 weeks earlyforecast Jun 30, 2014