Back to projects

Watermain Replacement and SMARThydrant Installation

Lincoln, Ontario

underwayDrinking WaterGIS
Federal contribution
$2.0M
$1,991,000
Federal share40%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
today
202220232024202520262027
BuiltForecast

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Lincoln
Construction start
Apr 1, 2023(actual)
Construction end
Oct 31, 2026(forecast)

Also in Lincoln