Improvements to Stormwater Quality on Groat Road Basin

Edmonton, Alberta

completeWastewaterISF
Federal contribution
$1.7M
$1,699,326
Federal share33%

of $5.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 31, 2011
2011
Built

Approved 4 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Edmonton
Construction start
Nov 10, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Dec 6, 2010