Improvements to Stormwater Quality on Groat Road Basin
Federal contribution
$1.7M
$1,699,326
Federal share33%
of $5.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 31, 2011
2011
Built
Approved 4 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Edmonton
- Construction start
- Nov 10, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Dec 6, 2010
Also in Edmonton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40959 in the federal list. How to read these figures.