Highway 1 Resurfacing - Nanaimo River Road to Spitfire Road
Federal contribution
$608,081
Federal share45%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 19, 2010
ApprovedSep 8, 2010
2011
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Sep 7, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Aug 1, 2010