City Hall (Main Building) Heating, Ventilation and Air Conditionning Replacement
Federal contribution
$266,666
Federal share33%
of $800.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 8, 2011
Built
Approved 7 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Peterborough
- Construction start
- Mar 14, 2011(actual)
- Construction end
- Oct 14, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Jan 3, 2011
- Construction end2 weeks earlyforecast Oct 31, 2011