Back to projects

Program for the renewal of drinking water and wastewater pipes

Montréal, Quebec

completeWastewaterISF
Federal contribution
$1.0M
$1,041,646
Federal share31%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2011
20102011
Built

Approved 7 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Montréal
Construction start
Jun 9, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 6, 2009
  • Construction end7 months lateforecast Mar 31, 2011

Also in Montréal